This web page contains a live and functional spreadsheet created with
SpreadsheetConverter
. Please enable JavaScript in your web browser for the live calculations to work properly.
INTRODUCTION
INTRODUCTION
Lvl1 Project Breakdown
EARLY SCOPE ASSESSMENTS & MANPOWER PLANNING
DATE
Print
MANPOWER COST CONTENT (For country/region/area where project is to be constructed) - Enter typical contractor type hourly charge rates (Number formats) in white cells below left and right. NOTE: Rates must be entered for every category.
CONSTRUCTION SCHEDULE? Enter in cell right - If 18 days - average work hours per day per site person(eg 9). If 18 weeks - hours per week(eg 45). If 18 months - hours per month(eg 195).
Site manpower categories
Average charge rate per hour
Site manpower categories (cont)
Average charge rate per hour
Senior site management/supervision (Incl expats)
Mechanical fitters/millwrights
Local supervisory personnel
Pipefitters/welders
Local administration staff
Electricians
Earthmoving plant operators/mechanics
Instrumentation technicians
Carpenters/bricklayers/steelworkers
Painters/insulators
Crane operators/riggers
Manual labourers
Boilermakers/plate welders
PROJECT LEVEL 1 BREAKDOWN - Enter total project value, excluding land purchase in
RED
cell below. Possible weightings (typical) are provided, but can be changed by User based on specific knowledge of the subject project. Note: Total 1.00 must be maintained for each 'weighting' column.
1.0. OVERALL PROJECT EXCL LAND PURCHASE
1.1. PROJECT MANAGEMENT
Expenditure
Weighting
Value
Expenditure
Weighting
Value
Project management
Project management team
Engineering & design
Team accommodation/admin
Procurement (All materials excl consumables)
Specialised consultants
Construction
Travel
Commissioning
IT
Project value (Location country's currency)
Project budget estimate
1.2. ENGINEERING & DESIGN
1.3. PROCUREMENT
Expenditure
Weighting
Value
Expenditure
Weighting
Value
Civils & structurals team
Structural steel
M E & I team (Incl protective cover)
Vessels, tanks, pumps, heaters etc
Piping team
Piping valves & fittings
Team accommodation/admin
Electrical materials
IT/CAD
Instrumentation materials
Project budget estimate
Project budget estimate
1.4. CONSTRUCTION
1.5. COMMISSIONING
Expenditure
Weighting
Value
Expenditure
Weighting
Value
1.4.1. Management & indirects
Commissioning team
1.4.2. Earthworks & civils
Equipment & tools
1.4.3. M E & I
Consumable materials
1.4.4. Piping & pipelines
Travel
1.4.5. Protective cover
IT & Admin
Project budget estimate
Project budget estimate
NOTES
Reset